Part 3: Kathleen's Office Flooring and Paint

202012

Navigation Links
 Trip Home Page     

 


The Trip

After seeing how good the vinyl tile looked in the living room and carefully considering the age of the carpeting in the balance of the house, we decided to replace all the carpet with tile.  As before, the lead times were substantial, but in due course the materials arrived.  As always, demolition is easy, installation less so.

The Photos

The photos below are what we saw.

The first act was to evacuate the items in Kathleen's office.  No small feat, but after several days, the items were migrated to other rooms.  Once the room was clean, removal of the carpet was easy.  Kathleen found a person anxious to take the cast-off carpet and padding.  When the padding was removed, we were ready to pull the tack strips and scrape the glue from the slab.

There was quite a bit of paint and drywall mud from the original construction of the house in 1978, but unlike the living room the total area was small and the scraping was completed in only a few hours.  Lots of tedious "hands-and-knees" work, but not hard.

Once the tack strips were removed and the floor was scraped, the whole area was cleaned with the shop vac to remove debris.

The scraping did take some labor, but most of the paint and carpet glue came off with the aid of scraping tools and some elbow grease.

After the scraping, the baseboards were removed and the holes in the slab left by the tack strip nails were filled with concrete patching compound.

Some of the areas were more damaged than others and required several layers of concrete patching material.

Next up was paint.  Kathleen's color of choice was "Americana Blue" and the original semi-gloss was covered with a flat finish.  One wall was selected to be the "accent" wall and a sunflower yellow was chosen.  Several coats were required to get full coverage.

The yellow was rather bold, but it DID provide the desired accent.  The door would be removed, sanded and repainted "cottage white".

When the painting was completed, the entire floor was vacuumed again to insure that no debris remained.

Once our tile arrived, we started the installation.  The tile snaps together, so assembly is fast once the prep-work is completed.  To insure tight joints, each "course" is seated with a mallet and block.  5mm plastic spacing blocks were used as reference to insure sufficient thermal expansion space for the tile.

Both the first and last course required ripping the planks length-wise to insure that the edge planks would not be too narrow.  Installing the last course required substantial care.

Our baseboard still had not arrived, so Kathleen decided to evaluate a new location for her desk.  Lighting in the room is an issue due to reflections off our neighbor's house.  The reflected light produces glare on the computer screen so some testing was required to get an adequate solution.  Here, her sewing table acts as a desk-proxy for evaluation of the lighting.

While we were waiting for delivery of the baseboard, Kathleen refinished her door using a power sander.

The baseboard finally arrived and a trip to the vendor was required to bring it home.  These pieces are 15' in length so a ladder was used to provide support during transport.  The ladder was ratchet-strapped to the truck and the baseboard was lashed to the ladder.

The baseboard was primed, but a coat of paint was required before installation.

Once the baseboard was painted and dried, it was  brought inside to protect it from the damp night air and placed alongside the other items that were office refugees.

My neighbor kindly offered his miter saw but his contracting assignments collided with our needs.  In the end, a trip to Home Depot got us what we needed: a 10" traveling, double bevel miter saw and an 18ga pneumatic nailer.  Both worked as expected.

The saw and nailer made completion of the room easy.  A bit of painter's putty and some touch-up paint are all that remain.  The bold yellow worked better than I had originally thought.

Migrating from the semi-gloss to flat finish greatly improved my affinity for the blue color.

Closet doors were removed and the space would be used to house a futon bed for guests.  Our new Stressless office chairs finally arrived after many months.


This portion of the enhancements spanned many months if you include the lead time for the chairs and tile.  But, once the components were on-site, installation was rapid.  As always, it was more complex than expected and took longer than desired, but we prevailed and were very pleased with the results..

Next: rehabilitation of my office.


Navigation Links
Previous Adventure
Top of this Page
  Next Adventure
Trip Home Page  
Bill Caid's Home Page

Photos and Text Copyright Bill Caid 2020, all rights reserved.
For your enjoyment only, not for commercial use.