Part 4: Sub-Frame Completion and Battery Box Fabrication

20100929-20101008

Navigation Links
 Trip Home Page     

 


The Trip

Progress was somewhat slow during this phase of construction.  There were a number of reasons, but in the end, substantial progress was made.  Hydraulic parts and a larger fuel tank were ordered and the detail design of the tire lift mechanism was completed.  Additionally, the generator was purchased in Pueblo along with the tire lift winch.

The photos below are what we saw.

New battery tie-downs were fabricated, primed, painted and installed. New truck batteries were acquired and installed as well.

After the frame articulation test shown in Part 3, our plan was to remove the camper, and then complete the sub-frame fabrication.  Above, Rob positions the fork lift to raise the camper.

The camper was then placed on jack stands for sub-frame modifications and other actions.


The articulation test showed that a mechanical interference was likely under extreme articulation.  So, rather than risk tweaking something, we decided to trim the sub-frame to provide additional clearance.  Above, the chalk lines show where the plasma torch will cut the frame.

The center frame member needed a bunch of additional welding done to complete the fabrication.

The tack welds on the center frame member would have to be hard welded before priming and painting.

The truck frame attachments were good as-is, so they were primed and painted.

The rear frame attachment was primed and painted as well.

Kathleen used an air buffer to remove surface rust and scale prior to priming the center frame member.

The rear member still needed some welding done to box the frame.

The rear frame member was left-right asymmetrical to provide clearance for the gray water plumbing.  It was boxed as well.

Rob found a spare Class III hitch to mount on the truck.  We used 3/8"x5" angle as the mounts.

The hitch was tweaked by use from the previous owner, so we straightened it as best we could and then welded in gussets to prevent further deformation.  Once completed, the hitch was attached with Grade 8 bolts and LocTite blue.

Next, Kathleen and I attacked the removable cargo basket mount.  The plan was to weld 2 trailer receivers on the top of the frame members and then plug the frame into them.  The bottom of the frame would be supported by an insert that goes into the main trailer receiver.  Above, we get the receivers true on the frame prior to tacking.

All corners on the basket frame were mitered cuts, so careful layout and cutting were required to get them to fit and be square.  Above, you can see the lower member bolted onto the trailer hitch receiver.

We measured and adjusted multiple times until we were sure it was correct.

Our diligence paid off; the frame was square and true on the first try.

Rob started on the fabrication of the house battery box.  This box was constructed out of 3/16' material and needed to hold nearly 300# of lead-acid batteries.

Above, Rob completed grinding after boxing the frame.

The front pivot mount is completed.

To mount the propane, we decided to co-opt existing holes in the frame.

The battery box and battery retainer straps were completed and awaiting painting.

The roof lift hydraulic pump was moved to the wheel well of the trailer and the pressure and return lines were moved to the new location.

The propane feed lines were modified and the lines to the refrigerator were moved.  The drain line from the refrigerator was moved as well.

Kathleen prepped, primed and painted the front mount and battery box.

The extra strap on the battery box is the mounting for the tire hydraulic pump.

When the battery box was completed, Rob moved on to the tire mount/headboard.

I designed an access ladder and fuel can rack to go on the driver's side of the headboard.  On top of the can rack, the generator will be mounted.


I purchased the generator on a day trip to Pueblo.  Above, you can see how the generator will sit on the can rack.

The rubber feet of the generator sit in the circular cups.

The cargo basket rack was cosmetically completed and painted.

A view of the completed battery box with 4 golf cart batteries installed awaiting wiring.

This was a lot of work that spanned many days.  We addressed some difficult geometry issues, but in the end always came up with an adequate solution.  Next, the camper will be re-mounted on the truck for "final" attachment.


Navigation Links
Previous Adventure
Top of this Page
  Next Adventure
Trip Home Page  
Bill Caid's Home Page

Photos and Text Copyright Bill Caid 2010, all rights reserved.
For your enjoyment only, not for commercial use.